A work order (sometimes called a notice to proceed, change directive, or site instruction) is the written document by which an owner or the owner's authorized representative (an architect, engineer, or construction manager) formally instructs a contractor to take a specific action on a construction or services contract: begin work, stop work, resume work, change the scope or method of performance, or adjust the schedule. It creates a dated, written record of exactly what was instructed and when, which becomes critical if a dispute later arises over delays, scope creep, or unpaid change-order costs. When to use it: any time an owner, general contractor, or construction manager needs to give a contractor or subcontractor a formal, written instruction that affects performance of the underlying contract — mobilizing on site, issuing a stop-work order, authorizing extra work, or extending a completion date. Verbal instructions on a job site are a leading cause of payment and delay disputes precisely because there is no record of what was actually said. A written work order closes that gap and gives both sides a document they can point to later. Legal basis: construction contracting in the United States is governed primarily by the general law of contracts (offer, acceptance, consideration, and the parties' course of dealing) rather than by a single federal statute. Most standard-form construction agreements — including the widely used AIA A201 General Conditions and ConsensusDocs family of documents — expressly define a "Change Order," "Construction Change Directive," or "Notice to Proceed" and require the contractor to comply with a properly issued written instruction even where the contractor disputes its validity, provided the contractor preserves its rights by submitting a timely written protest or claim as specified in the contract. Public construction contracts (federal, state, or municipal) are frequently subject to additional statutory or regulatory change-order and claims procedures (for example, the Federal Acquisition Regulation's "Changes" clause on federal projects, or state public-contracting codes), and many states impose specific notice deadlines for a contractor to preserve a claim for extra time or money. Because rules vary significantly by state, by project type (public vs. private), and by the governing contract form, this template uses general contract-law language rather than citing a specific statute — the parties should confirm which contract terms, statutes, or licensing rules apply to their particular project before relying on it. Parties: the issuer (the owner, or the owner's authorized representative such as an architect, engineer, or construction manager acting on the owner's behalf) and the recipient (the contractor holding the contract, or the relevant subcontractor if the project is broken into separate trade contracts). Key clauses: a unique work order number and issue date; a clear reference to the underlying contract or purchase order; the precise nature of the instruction (mobilize/start, stop, resume, change scope, or extend/compress schedule); the effective date on which the instruction takes hold; and a statement of any resulting cost or schedule impact, including whether the contractor must submit a claim or protest to preserve rights to additional compensation or time. Effects: once properly issued under the contract, a work order is generally binding on the contractor, who is typically expected to proceed with the instructed work even while reserving the right to dispute its cost or schedule impact — provided the contractor submits written notice of its objection or claim within whatever notice period the contract specifies. Missing that notice window is one of the most common ways contractors lose an otherwise valid claim for extra compensation. A work order that changes scope, method, or schedule may separately trigger a right to a change order or equitable adjustment if the underlying contract provides for one. Common mistakes to avoid: relying on a verbal or emailed instruction instead of issuing (and keeping a copy of) a formal written work order; leaving out the effective date, which creates ambiguity about exactly when the contractor's obligations changed; failing to state whether the instruction has cost or schedule consequences, leaving both parties to guess; and, on the contractor's side, failing to submit a timely written protest or claim when disputing the work order's validity, cost impact, or schedule impact — since most contracts treat silence within the notice period as a waiver of the claim.
Issuer name (owner or authorized representative)
Issuer's role
Owner, or an architect/engineer/construction manager acting as the owner's authorized representative.
Recipient name or company (contractor)
Reference and description of the underlying contract
Work order number
Date of this work order
Type of instruction (start, stop, resume, change scope, extend/compress schedule)
Detailed description of the instruction
Effective date of the instruction
Impact on cost and/or schedule, if any
Number of days the contractor has to submit a written protest or claim, per the contract
Owner, or an architect/engineer/construction manager acting as the owner's authorized representative.