A construction subcontractor agreement is the contract between a general contractor (GC) and a subcontractor hired to perform a defined portion of a construction project — framing, electrical, plumbing, HVAC, drywall, concrete, roofing, and similar specialty trades. It sits underneath the prime contract between the general contractor and the project owner: the subcontractor has no direct contractual relationship with the owner, and payment flows through the general contractor rather than from the owner directly. Use this agreement whenever a general contractor engages an independent subcontractor to perform part of a construction project, whether the underlying job is private commercial work, private residential work, or a portion of a public project the GC was awarded. It is not the right document for two contractors jointly and directly contracting with the owner (a joint venture or teaming arrangement), and it is not a substitute for a purchase order covering pure material supply with no labor or installation component. Legal basis: construction subcontracts are governed primarily by general contract law and by state-specific construction statutes, which vary significantly by jurisdiction — there is no single federal subcontracting statute comparable to France's 1975 subcontracting law. Three bodies of law recur across states and should be checked against the applicable jurisdiction before use: (1) mechanic's lien and payment bond statutes, which give unpaid subcontractors a lien right against the property (private work) or a bond claim right (public work under the federal Miller Act, 40 U.S.C. §§ 3131–3134, or a state "Little Miller Act") — lien and bond claim deadlines are short and strictly enforced, often 60–120 days from last furnishing labor or materials; (2) prompt payment statutes, adopted in most states, which require the GC to pay the subcontractor within a set number of days after receiving payment from the owner and impose interest penalties for late payment; and (3) state licensing requirements for contractors and subcontractors, violation of which can bar a subcontractor from enforcing payment in court in some states even where the work was properly performed. Because these rules differ materially state to state, the jurisdiction field in this template should be filled with the state whose law will govern, and the parties should confirm current lien-notice and licensing requirements for that state before signing. Key clauses: a precise description of the subcontracted scope of work (cross-referenced to the prime contract's drawings and specifications, since the subcontractor is bound by the terms of the prime contract as they relate to its scope — a "flow-down" clause); the contract price and payment schedule, including progress payments, the timing of payment relative to the GC's own receipt of payment from the owner ("pay-if-paid" versus "pay-when-paid" clauses, which are enforceable in some states and void or limited in others); retainage — the percentage withheld from each payment until substantial or final completion; lien waiver and release requirements conditioning progress payments on the subcontractor's waiver of lien rights for amounts already paid; the schedule and time for completion, including provisions for delay and liquidated damages; insurance requirements (commercial general liability, workers' compensation, and often an additional-insured endorsement naming the GC and owner); and indemnification, obligating the subcontractor to defend and hold the GC harmless for claims arising from the subcontractor's work, subject to state anti-indemnity statutes that limit or void indemnification for the indemnitee's own negligence in many states. Common mistakes to avoid: omitting a flow-down clause, which leaves the subcontractor unbound by prime-contract terms the GC needs it to honor (safety plans, change-order procedures, dispute-resolution mechanics); using a "pay-if-paid" clause in a state where such clauses are unenforceable, creating false confidence about payment timing; failing to track lien and bond-claim notice deadlines, which are jurisdictional and cannot be extended after they lapse; skipping written change orders for scope changes, which weakens the subcontractor's ability to recover for extra work; and confusing a subcontractor relationship with an independent-contractor-versus-employee misclassification issue — this agreement assumes the subcontractor is itself a licensed business entity, not an individual whose worker classification is in question.
General contractor's legal name
General contractor's business address
Subcontractor's legal name
Subcontractor's business address
Subcontractor's contractor license number
Include if the state requires contractor licensing for this trade.
Project owner's name
Reference and description of the prime contract
Project site address
Description of the subcontracted scope of work
Subcontract price (USD)
Payment schedule and terms
Payment timing relative to owner payment (pay-if-paid, pay-when-paid, or fixed schedule)
Retainage percentage withheld from each payment
Work start date
Time allowed for completion
Liquidated damages for delay, if any
Required insurance coverage and minimum limits
Governing state